March 4, 2024
As we continue to expand with the successful launch of North Harbour Business Park, we’re thrilled to share progress on our latest road construction. But some fun facts and figures first.
Detail approvals required following preliminary approval, for commencement of construction –
Since completing design and gaining the above-mentioned approvals construction has been progressed very well despite significant challenges, namely the 2764mm of rain that has fallen and some 140 days of delay due to inclement weather.
The rain delays have allowed detailed design and approval of other major infrastructure for North Harbour to catch up to road construction. As a result, 2000m of water main pipework is currently being installed alongside North Harbour Boulevard. Constructing this now will avoid lane closures and traffic delays once North Harbour Blvd is open to traffic.
We’re pressing on with an anticipated opening date of November 2024 as currently programmed. We had hoped to open the road earlier however with 50 working weeks delay due to inclement weather since commencement this has been challenging.
Thank you for your patience and understanding as we work towards completing this important project.