As we continue to expand with the successful launch of North Harbour Business Park, we’re thrilled to share progress on our latest road construction. But some fun facts and figures first.

  • Road Type – 2 lane Sub Arterial with land dedicated (average 56.5m width) for future upgrade to 4 lane Arterial .
  • Length – 2215m
  • Intersections – 3 (all to be signalised) 
  • Bridges – 1 
  • Culvert crossings – 2 
  • Number of pipes installed – 850
  • Diameter of biggest pipe – 2050mm
  • Dirt Moved – 400,000m3
  • Number of machines during peak construction – 60

Detail approvals required following preliminary approval, for commencement of construction  – 

  • Bulk earth works – COMB 
  • Operational Works (OPW) Civil construction – COMB 
  • OPW Civil construction Intersection 1 – COMB
  • OPW Civil construction Intersection 2 – COMB
  • OPW Civil construction Intersection 3 – COMB
  • Landscape Approval – COMB 
  • Electrical – Energex
  • Water reticulation – Unity Water 
  • Department of Environment 
  • Department of Transport and Main Roads
  • Department of Agriculture and Fishers 
  • Road design period – 22 Months 
  • Number of Environmental basins

Since completing design and gaining the above-mentioned approvals construction has been progressed very well despite significant challenges, namely the 2764mm of rain that has fallen and some 140 days of delay due to inclement weather.  

The rain delays have allowed detailed design and approval of other major infrastructure for North Harbour to catch up to road construction.  As a result, 2000m of water main pipework is currently being installed alongside North Harbour Boulevard.  Constructing this now will avoid lane closures and traffic delays once North Harbour Blvd is open to traffic.

We’re pressing on with an anticipated opening date of November 2024 as currently programmed. We had hoped to open the road earlier however with 50 working weeks delay due to inclement weather since commencement this has been challenging.

Thank you for your patience and understanding as we work towards completing this important project.

Find Us 

North Harbour Homes will be operating out of the North Harbour’s Sales and Information Centre and Display Village. The sales office is open seven days a week, 10am-5pm, located on the corner of Buckley Road and Fraser Drive in Burpengary East.

 

*Any product pricing and availability referenced in this or other North Harbour articles are accurate at the date of initial publication and are subject to change at any time without notice.  Please contact the North Harbour sales team for further information. 

 

North Harbour © 2024 North Harbour Disclaimer and Terms & Conditions Sitemap | * Marina is subject to government approvals

* Any product pricing and availability referenced in this North Harbour website are accurate at the date of initial publication and are subject to change at any time without notice. Please contact North Harbour sales team for further information.

Call
Directions
Facebook
Instagram